Heat Exchanger

We developed the engineering for the fabrication of a heat exchanger of 96“ diameter and 1/4” thickness, with 238" length.

Installation of stairs to 3 levels

Manufacture and installation of stairs in 3 levels, in a time of 4 days of manufacture and 2 days of installation..

Fabrication and installation of roofing

Fabrication and installation of a 250 mts long x 6 mts wide, double fall and 10 mts high roof.

Fabrication and erection of Road Arch

We manufacture the structure in structural HSS, PTR, some components cut and bent based on AWS D1.1 welding, performing the civil works on site, excavation, concrete footings and assembly, and subcontracting the galvanizing service by immersion.

Manufacture of pipe supports

Manufacture of pipe supports according to ASME B31-2020 code, we cut, weld, sandblast and apply epoxy paint.